Friday, 16 August 2013

Work on site is now complete and it is ready to handover



Friday, 21 June 2013

The subcontractors are pressing on with the internals with the first and second fix of the mechanical and electrical fittings, this allows for the joiners to fit the kitchens.
 
 

Monday, 17 June 2013

The rainwater harvesting tank has been installed this week, it will be used to store rainwater collected from the roofs and then supply this water to the ground floor properties for flushing toilets.
 
 
 

Monday, 3 June 2013

The feeder pillar is installed with ducting fed into the base in preparation for site electric supplies for external lighting, rainwater harvesting and the TV aerials.  It is located in the cycle store and will  be fixed in place when the gravel base and concrete is poured.
 
 

Wednesday, 29 May 2013

With the plaster boarding and skim complete, the installation of the services can resume.
 
 

Monday, 13 May 2013

The facing brickwork is now complete to the underside of the eaves.



Friday, 26 April 2013

With the block now watertight the plaster boarding can begin internally while the bricklayers build up the facework externally with the help of hop-ups which are intermediate levels of scaffolding.